HOTO Plan β€” Gantt View

Project Tiger Β· Dhaly Infratech → Alliance Computers Limited Β· Scheduling & priority timeline
Dhaly → Alliance · Narayanganj | Feb 24 – Mar 15, 2020 | 2 Sites | 2 Done | 0 Pending
All Districts 2 Habiganj 10 Kishoreganj 8 Moulavibazar 13 Narayanganj 2 Narsingdi 22 Sunamganj 21 Sylhet 24
Phase 1 (default) — pending Phase 2 — pending Phase 3 — pending Completed Click Assigned To / phase to edit
Site Code Thana Assigned To Feb 24
Mon
Feb 25
Tue
Feb 26
Wed
Feb 27
Thu
Feb 28
Fri
Feb 29
Sat
Mar 1
Sun
Mar 2
Mon
Mar 3
Tue
Mar 4
Wed
Mar 5
Thu
Mar 6
Fri
Mar 7
Sat
Mar 8
Sun
Mar 9
Mon
Mar 10
Tue
Mar 11
Wed
Mar 12
Thu
Mar 13
Fri
Mar 14
Sat
Mar 15
Sun
0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0
Narayanganj 2 Sites
DHK_G4393 Araihazar
DHK_X2727 Araihazar