HOTO Plan β€” Gantt View

Project Tiger Β· Dhaly Infratech → Alliance Computers Limited Β· Scheduling & priority timeline
Dhaly → Alliance · Moulavibazar, Habiganj, Narayanganj | Oct 2 – Oct 22, 2028 | 25 Sites | 12 Done | 13 Pending
All Districts 25 Habiganj 10 Kishoreganj 8 Moulavibazar 13 Narayanganj 2 Narsingdi 22 Sunamganj 21 Sylhet 24
Phase 1 (default) — pending Phase 2 — pending Phase 3 — pending Completed Click Assigned To / phase to edit
Site Code Thana Assigned To Oct 2
Mon
Oct 3
Tue
Oct 4
Wed
Oct 5
Thu
Oct 6
Fri
Oct 7
Sat
Oct 8
Sun
Oct 9
Mon
Oct 10
Tue
Oct 11
Wed
Oct 12
Thu
Oct 13
Fri
Oct 14
Sat
Oct 15
Sun
Oct 16
Mon
Oct 17
Tue
Oct 18
Wed
Oct 19
Thu
Oct 20
Fri
Oct 21
Sat
Oct 22
Sun
0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0
Habiganj 10 Sites
SYL_X0083 Ajmiriganj
SYL_X0291 Bahubal
SYL_X0072 Baniachong
SYL_X0222 Chunarughat
SYL_X0331 Habiganj Sadar
SYL_X0604 Habiganj Sadar
SYL_X0082 Lakhai
SYL_X0117 Lakhai
SYL_X0566 Lakhai
SYL_X0052 Nabiganj
Moulavibazar 13 Sites
SYL_X0141 Barlekha
SYL_X0213 Barlekha
SYL_X0075 Juri
SYL_X0105 Kamalganj
SYL_X0067 Kulaura
SYL_X0103 Kulaura
SYL_X0615 Kulaura
SYL_X0092 Moulavibazar
SYL_X0550 Moulavibazar
SYL_X0097 Moulvibazar Sadar
SYL_X0257 Moulvibazar Sadar
SYL_X0364 Moulvibazar Sadar
SYL_X0077 Rajnagar
Narayanganj 2 Sites
DHK_G4393 Araihazar
DHK_X2727 Araihazar