HOTO Plan β€” Gantt View

Project Tiger Β· Dhaly Infratech → Alliance Computers Limited Β· Scheduling & priority timeline
Dhaly → Alliance · Kishoreganj | Oct 30 – Nov 19, 2023 | 8 Sites | 0 Done | 8 Pending
All Districts 8 Habiganj 10 Kishoreganj 8 Moulavibazar 13 Narayanganj 2 Narsingdi 22 Sunamganj 21 Sylhet 24
Phase 1 (default) — pending Phase 2 — pending Phase 3 — pending Completed Click Assigned To / phase to edit
Site Code Thana Assigned To Oct 30
Mon
Oct 31
Tue
Nov 1
Wed
Nov 2
Thu
Nov 3
Fri
Nov 4
Sat
Nov 5
Sun
Nov 6
Mon
Nov 7
Tue
Nov 8
Wed
Nov 9
Thu
Nov 10
Fri
Nov 11
Sat
Nov 12
Sun
Nov 13
Mon
Nov 14
Tue
Nov 15
Wed
Nov 16
Thu
Nov 17
Fri
Nov 18
Sat
Nov 19
Sun
0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0 0/0 0/0 0/0 0/0 Off 0/0 0/0
Kishoreganj 8 Sites
DHK_X0231 Bhairab
DHK_X1806 Bhairab
DHK_X2655 Bhairab
DHK_X3450 Bhairab
DHK_X4428 Bhairab
DHK_X1669 Kuliarchar
DHK_X2656 Kuliarchar
DHK_X4606 Kuliarchar